Calculation
230
Your Quantity
Rate by
Brick work with first class bricks in foundation (1:6)(100 cft)
MaterialquantityUnitRateAmount
Bricks 1,100.00Nos 14.17 15587
Sand 1.2 FM 36.00cft 53.55 1927.8
Cement 4.00bag 603.75 2415
Head Masson (Civil) 0.10person 920.00 92
Masson (Civil) 1.00person 770.00 770
Ordinary Labour 1.50person 638.00 957
Skill Labour (civil) 1.00person 660.00 660
Unskilled Labour 2.00person 472.50 945
Unskilled Labour 2.00person 472.50 945