Calculation
230
Your Quantity
Rate by
Brick work with first class bricks in superstructure (1:6)(100 cft)
Material | quantity | Unit | Rate | Amount |
---|---|---|---|---|
Scaffolding | 25.00 | sft | 0 | |
Ordinary Labour | 2.25 | person | 638.00 | 1435.5 |
Bricks | 1,100.00 | Nos | 14.17 | 15587 |
Sand 1.2 FM | 36.00 | cft | 53.55 | 1927.8 |
Cement | 4.00 | bag | 603.75 | 2415 |
Head Masson (Civil) | 0.10 | person | 920.00 | 92 |
Skill Masson (Civil) | 1.00 | person | 787.50 | 787.5 |
Skill Labour (civil) | 2.50 | person | 660.00 | 1650 |