Calculation
230
Your Quantity
Rate by
125 mm brick work with first class bricks (1:6) in superstructure(100 sft)
Material | quantity | Unit | Rate | Amount |
---|---|---|---|---|
Bricks | 480.00 | Nos | 14.17 | 6801.6 |
Sand 1.2 FM | 18.00 | cft | 53.55 | 963.9 |
Cement | 1.75 | bag | 603.75 | 1056.5625 |
Head Masson (Civil) | 0.10 | person | 920.00 | 92 |
Skill Masson (Civil) | 0.75 | person | 787.50 | 590.625 |
Ordinary Labour | 3.00 | person | 638.00 | 1914 |
Skill Labour (civil) | 0.50 | person | 660.00 | 330 |
Scaffolding | 25.00 | sft | 0 |