125 mm brick work with 10 hole machine made ceramic bricks (1:4) in superstructure(100 sft)
MaterialquantityUnitRateAmount
Bricks 480.00Nos 14.17 6801.6
Sand 1.2 FM 18.00cft 53.55 963.9
Cement 2.80bag 603.75 1690.5
Head Masson (Civil) 0.10person 920.00 92
Masson (Civil) 1.00person 770.00 770
Ordinary Labour 1.00person 638.00 638
Unskilled Labour 2.00person 472.50 945
Skill Labour (civil) 0.50person 660.00 330
Scaffolding 25.00sft 0
Miscellaneous (taka) 300.00LS 1.14 342