Calculation
230
Your Quantity
Rate by
125 mm brick work with 10 hole machine made ceramic bricks (1:4) in superstructure(100 sft)
Material | quantity | Unit | Rate | Amount |
---|---|---|---|---|
Bricks | 480.00 | Nos | 14.17 | 6801.6 |
Sand 1.2 FM | 18.00 | cft | 53.55 | 963.9 |
Cement | 2.80 | bag | 603.75 | 1690.5 |
Head Masson (Civil) | 0.10 | person | 920.00 | 92 |
Masson (Civil) | 1.00 | person | 770.00 | 770 |
Ordinary Labour | 1.00 | person | 638.00 | 638 |
Unskilled Labour | 2.00 | person | 472.50 | 945 |
Skill Labour (civil) | 0.50 | person | 660.00 | 330 |
Scaffolding | 25.00 | sft | 0 | |
Miscellaneous (taka) | 300.00 | LS | 1.14 | 342 |