Break Up Details (Don's use Rate, its PWD rate 2008)

Setting out: providing layout, bench-mark, property line, formation level etc.
Considering 5000 sft ground area
1. Surveyor 1 No. @ 450 per day = 450
2. Helper to surveyor 1 No. @ 300 per day = 300
3. Hire charge of Level/Theodolite 1 set 600 per day = 600
4. Ordinary labour 2 No. @ 150 per day = 300
5. Cost for construct and protect bench-mark, test pit etc. L.S. = 4600
6. Tools and plant, spike, nails, chalk-powder etc. L.S. = 375
Total = 6625
Profit 0.1 = 662.5
Overhead 0.035 = 231.88
7519.38
Add VAT with adjustment factor 1.04712 0.045 = 354.32
Grand total = 7873.7
Rate per sft. = 1.57
Rate per sqm. = 16.9
Say, 17 .00 Per sqm.