Break Up Details (Don's use Rate, its PWD rate 2008)

Earth filling in foundation trenches and plinth (earth available at site)
Considering 1000 cft. of work
1. Labour for filling
including local carriage 8 Nos. @ 150 each = 1200
3. Skilled labour for dressing
& consolidation 2 Nos. @ 200 each = 400
4. Sundries, T & P etc. L.S. = 75
Total = 1675
Profit 0.1 = 167.5
Overhead 0.035 = 58.63
1901.13
Add VAT with adjustment factor 1.04712 0.045 = 89.58
Grand total = 1990.71
Rate per cft. = 1.99
Rate per cum. = 70.28
Say, 70 .00 Per cum.