Break Up Details (Don's use Rate, its PWD rate 2008)

Earth filling in foundation trenches with carted earth carried by truck or any other means
Considering 1000 cft. of work in/c compacting, dressing and local carriage
(d) For other than Dhaka, Ctg., Sylhet, Rajshahi, Barishal, Khulna metropolitan area and N'ganj district
Loose earth required in/c 15% shrinkage = 1150 cft.
1. Royalty for earth 1150 cft. @ 300 Per % 0 cft. = 345
2 Truck hire charge including cost of labour for loading and unloading 6 Trucks @ 600 Per truck = 3600
3 Labour for local carriage, levelling & compacting etc. complete:
(a) Ordinary labour 6 Nos. @ 150 each = 900
(b) Skilled labour 1 No. @ 200 each = 200
4 Sundries, T & P etc. L.S. = 45
Total = 5090
Profit 0.1 = 509
Overhead 0.035 = 178.15
5777.15
Add VAT with adjustment factor 1.04712 0.045 = 272.22
Grand total = 6049.37
Rate per cft. = 6.05
Rate per cum. = 213.66
Say, 214 .00 Per cum.