Break Up Details (Don's use Rate, its PWD rate 2008)

One layer brick flat soling in foundation or in floor.
Considering 100 sft of work
1. Bricks 300 Nos. @ 5000 Per % 0 Nos. = 1500
2. Fine sand 5 cft. @ 750 Per % cft. = 37.5
3. Mason 0.25 No. @ 250 each = 62.5
4. Skilled labour 1 No. @ 200 each = 200
5. Local carriage, sundries, T & P etc. L.S. = 30
Total = 1830
Profit 0.1 = 183
Overhead 0.035 = 64.05
2077.05
Add VAT with adjustment factor 1.04712 0.045 = 97.87
Grand total = 2174.92
Rate per sft. = 21.75
Rate per sqm. = 234.12
Say, 234 .00 Per sqm.