Break Up Details (Don's use Rate, its PWD rate 2008)

One layer herrring bone bond soling in foundation or in floor.
Considering 100 sft of work
1. Bricks 500 Nos. @ 5000 Per % 0 Nos. = 2500
2. Fine sand 10 cft. @ 750 Per % cft. = 75
3. Mason 0.33 No. @ 250 each = 82.5
4. Skilled labour 1 No. @ 200 each = 200
5. Local carriage, sundries, T & P etc. L.S. = 45
Total = 2902.5
Profit 0.1 = 290.25
Overhead 0.035 = 101.59
3294.34
Add VAT with adjustment factor 1.04712 0.045 = 155.23
Grand total = 3449.57
Rate per sft. = 34.5
Rate per sqm. = 371.36
Say, 371 .00 Per sqm.