Break Up Details (Don's use Rate, its PWD rate 2008)

Brick on end edging
Considering 100 rft of work
1. Bricks 250 Nos. @ 5000 Per % 0 Nos. = 1250
2. Fine sand 2 cft. @ 750 Per % cft. = 15
3. Mason 0.2 No. @ 250 each = 50
4. Skilled labour 0.75 No. @ 200 each = 150
5. Local carriage, sundries, T & P etc. L.S. = 22.5
Total = 1487.5
Profit 0.1 = 148.75
Overhead 0.035 = 52.06
1688.31
Add VAT with adjustment factor 1.04712 0.045 = 79.55
Grand total = 1767.86
Rate per rft. = 17.68
Rate per rm. = 58.01
Say, 58 .00 Per rm.