Break Up Details (Don's use Rate, its PWD rate 2008)

Extra rate over the rate of form work / shuttering (wooden) of RCC works in columns, capitals, liftwalls & walls where the free height of the
structure exceeds 4 meter [rate is considered for the height of each addl. 4 (four) meter or part]
Considering 1 sqm.
(a) Extra for scaffolding [5% of shuttering or form work
using wooden shutter for column, pedestal etc.) L.S. = 11.72
Total = 11.72
Profit 0.1 = 1.17
Overhead 0.035 = 0.41
= 13.3
Add VAT with adjustment factor 1.04712 0.045 = 0.63
Grand total = 13.93
Say, 14 .00 Per sqm.