Break Up Details (Don's use Rate, its PWD rate 2008)

Extra rate over the rate of RCC (materials, consumables and laying/placing concrete) works in Tee beams, Ell beams and rectangular beams where the
free height of the structure exceeds 4 meter (rate is considered for each addl. meter height)
Considering 100 cft. of work
(a) Extra head mason 0.1 No. @ 350 each = 35
(b) Extra mason 0.2 No. @ 250 each = 50
(c) Extra skilled labour 0.2 No. @ 200 each = 40
(d) Extra ordinary labour 1 No. @ 150 each = 150
(e) Extra for local carriage, storage & sundries etc. L.S. = 15
Total = 290
Profit 0.1 = 29
Overhead 0.035 = 10.15
= 329.15
Add VAT with adjustment factor 1.04712 0.045 = 15.51
Grand total = 344.66
Rate per cft. = 3.45
Rate per cum. = 121.84
Say, 122 .00 Per cum.