Break Up Details (Don's use Rate, its PWD rate 2008)

Extra rate over the rate of form work / shuttering (wooden) of RCC works in Tee beams, Ell beams and rectangular beams where the
free height of the structure exceeds 4 meter (rate is considered for each addl. meter height)
Considering 1 sqm.
(a) Extra for scaffolding [10% of cost for shuttering/ formwork
using wooden shutter for Ell beams, Rectangular beams etc.] L.S. = 27.13
Total = 27.13
Profit 0.1 = 2.71
Overhead 0.035 = 0.95
= 30.79
Add VAT with adjustment factor 1.04712 0.045 = 1.45
Grand total = 32.24
Say, 32 .00 Per sqm.