Break Up Details (Don's use Rate, its PWD rate 2008)

Extra rate over the rate of RCC (materials, consumables and laying/placing concrete) works in columns, capitals, liftwalls & walls where the free height of the
structure exceeds 4 meter [rate is considered for the height of each addl. 4 (four) meter or part]
Considering 100 cft. of work
(a) Extra head mason 0.1 No. @ 350 each = 35
(b) Extra mason 0.2 No. @ 250 each = 50
(c) Extra skilled labour 0.2 No. @ 200 each = 40
(d) Extra ordinary labour 1 No. @ 150 each = 150
(e) Extra for local carriage, storage & sundries etc. L.S. = 9
Total = 284
Profit 0.1 = 28.4
Overhead 0.035 = 9.94
= 322.34
Add VAT with adjustment factor 1.04712 0.045 = 15.19
Grand total = 337.53
Rate per cft. = 3.38
Rate per cum. = 119.36
Say, 119 .00 Per cum.