Break Up Details (Don's use Rate, its PWD rate 2008)

Mild steel work in roof truss
Considering 50 kg of work
(i) M.S. sections in/c 3% wastage 51.5 kg @ 67 Per kg. = 3450.5
(ii) Fabrication, fitting, fixing revetting,
welding and hoisting in/c cost of revets,
bolts etc, and painting complete. 50 kg @ 26.67 Per kg. = 1333.5
Total = 4784
Profit 0.1 = 478.4
Overhead 0.035 = 167.44
= 5429.84
Add VAT with adjustment factor 1.04712 0.045 = 255.86
Grand total = 5685.7
Rate per quintal = 11371.4
Say, 11371 .00 Per quintal