Break Up Details (Don's use Rate, its PWD rate 2008)

Construction of expansion joint in RCC floor/ roof slabs or beams with V-folded copper sheet.
Considering 10 rft. of work
1. Cost of (2 x 4'-0" + 2 x 3-0" + 2" av.)
= 16" width copper sheet: 13.33 sft. @ 150 Per sft. = 1999.5
2. Mason 1 Nos. @ 250 each = 250
3. Skilled labour 1 Nos. @ 200 each = 200
4. Cost of mastic or hot bitumenous
sealing compound fill 10 rft. @ 86.67 Per rft = 866.7
Total = 3316.2
Profit 0.1 = 331.62
Overhead 0.035 = 116.07
= 3763.89
Add VAT with adjustment factor 1.04712 0.045 = 177.36
Grand total = 3941.25
Rate per rft. = 394.13
Rate per rm = 1293.14
Say, 1293 .00 Per rm.