Break Up Details (Don's use Rate, its PWD rate 2008)

Construction of expansion joint in RCC floor/ roof slabs or beams with V-folded Aluminium Water Stop sheet.
Considering 10 rft. of work
1. Cost of (2 x 4'-0" + 2 x 0'-3" + 2" av.)
= 16" width aluminium sheet: 13.33 sft. @ 115 Per sft. = 1532.95
2. Mason 1 Nos. @ 250 each = 250
3. Skilled labour 1 Nos. @ 200 each = 200
4. Cost of mastic or hot bitumenous
sealing compound fill 10 rft. @ 86.67 Per rft = 866.7
Total = 2849.65
Profit 0.1 = 284.97
Overhead 0.035 = 99.74
= 3234.36
Add VAT with adjustment factor 1.04712 0.045 = 152.4
Grand total = 3386.76
Rate per rft. = 338.68
Rate per rm = 1111.21
Say, 1111 .00 Per rm.