Break Up Details (Don's use Rate, its PWD rate 2008)

Construction of expansion joint in RCC floor/ roof slabs or beams with V-folded Aluminium Water
Stop sheet and 1/4" thick M.S. Plate..
Considering 10 rft. of work
1. Cost of (2 x 4'-0" + 2 x 0'-3" + 2" av.)
= 16" width aluminium sheet: 13.33 sft. @ 115 Per sft. = 1532.95
2. Cost of 1/4" thick & 6" wide M.S. plate:
@ 10.20 Ib per sft. 5 sft.
= 51.05 Ibs @ 38.55 Per Ib = 1967.98
3. Mason 1 Nos. @ 250 each = 250
4. Skilled labour 2 Nos. @ 200 each = 400
5. Cost of mastic or hot bitumenous
sealing compound fill and
fabrication of steel plate etc. 10 rft. @ 95.33 Per rft = 953.3
Total = 5104.23
Profit 0.1 = 510.42
Overhead 0.035 = 178.65
= 5793.3
Add VAT with adjustment factor 1.04712 0.045 = 272.98
Grand total = 6066.28
Rate per rft. = 606.63
Rate per rm = 1990.35
Say, 1990 .00 Per rm.