Break Up Details (Don's use Rate, its PWD rate 2008)

Labour for breaking head of cast-in-situ bored pile/pre-cast driven pile
Considering 1 cum. of work
(a) Skilled labour 7 Nos. @ 200 each = 1400
(b) Ordinary labour 2 Nos. @ 150 each = 300
(c) Repairing of pile head in/c materials L.S. = 125
(d) Straightening and bending of pile bars,
tools & plant, sundries etc. L.S. = 125
Total = 1950
Profit 0.1 = 195
Overhead 0.035 = 68.25
= 2213.25
Add VAT with adjustment factor 1.04712 0.045 = 104.29
Grand total = 2317.54
Say, 2318 .00 Per cum.