Break Up Details (Don's use Rate, its PWD rate 2008)

Wood works in frame of roof truss and wall plates
Considering 1 cft. of work
For Garjan / Local Sal wood/Jam
(a) Cost of wood in/c 5% wastage 1.05 cft. @ 1300 Per cft. = 1365
(b) Coaltering: 2 coats 14 sft. @ 5 Per sft. = 70
(c) Cost of nuts, bolts and nails 1 kg. @ 102 Per kg. = 102
(d) Labour for making, fitting & fixing
(i) Carpenter 0.25 No. @ 300 each = 75
(ii) Carpenter helper 0.25 No. @ 200 each = 50
Total = 1662
Profit 0.1 = 166.2
Overhead 0.035 = 58.17
= 1886.37
Add VAT with adjustment factor 1.04712 0.045 = 88.89
Grand total = 1975.26
Rate per cft. = 1975.26
Rate per cum. = 69756.31
Say, 69756 .00 Per cum.