Break Up Details (Don's use Rate, its PWD rate 2008)

Groove cutting 38mm x 6mm in cement plaster (1:2) to wall at outer surface of window top and bottom level
Break-up for 25 rft
1. Mason 0.1875 No. @ 250 each = 46.88
2. Skilled labour 0.1875 No. @ 200 each = 37.5
3. Curing, tools and plant, sundries LS = 25
Total = 109.38
Profit 0.1 = 10.94
Overhead 0.035 = 3.83
= 124.15
Add VAT with adjustment factor 1.04712 0.045 = 5.85
Grand total = 130
Rate per rft. = 5.2
Rate per rm = 17.06
Say 17 .00 per rm.