Break Up Details (Don's use Rate, its PWD rate 2008)

3" thick cornice of brick masonry (1:6)
Considering 100 rft. of work
(a) 0'-3" x 0'-3" Brick work (1:6) 6.25 cft. @ 91.27 Per cft. = 570.44
(b) Extra labour for brick moulding
& plastering 100 rft. @ 15 Per rft. = 1500
(c) (3" + 3" + 3")= 9" width
and 1/2" thick cement plaster (1:6)
from item No. 123(a) - I 75 sft @ 10.73 Per sft. = 804.75
Total = 2875.19
Profit 0.1 = 287.52
Overhead 0.035 = 100.63
= 3263.34
Add VAT with adjustment factor 1.04712 0.045 = 153.77
Grand total = 3417.11
Rate per rft. = 34.17
Rate per rm. = 112.11
Say, 112 .00 Per rm.