Break Up Details (Don's use Rate, its PWD rate 2008)

Minimum 1/2" thick cement plaster (1:4) with neat cement finishing to dado
(average of 1/2" on one side and 3/4" on other side).
For 3/4" thick plaster with neat cement finish on walls
Considering 100 sft. of work
(a) Sand (F.M. 1.2) 7.5 cft. @ 1300 Per % cft. = 97.5
(b) Cement 2 bags @ 370 Per bag = 740
(c) Labour =
(i) Head mason 0.25 No. @ 350 each = 87.5
(ii) Mason 1.25 Nos. @ 250 each = 312.5
(iii) Ordinary labour 1.25 Nos. @ 150 each = 187.5
(d) Washing of sand, local carriage, curing, & sundries etc. L.S. = 150
Total = 1575
Profit 0.1 = 157.5
Overhead 0.035 = 55.13
= 1787.63
Add VAT with adjustment factor 1.04712 0.045 = 84.23
Grand total = 1871.86
Average of 1/2"[from item No. 123 (a-ii)] and 3/4" = 1742.61
Rate per sft. = 17.43
Rate per sqm. = 187.62