Break Up Details (Don's use Rate, its PWD rate 2008)

B. For 1/4" thick cement plaster (1:3) to walls
(a) Sand (F.M. 1.2) 2.35 cft. @ 1300 Per % cft. = 30.55
(b) Cement 0.625 bag @ 370 Per bag = 231.25
(c) Labour
(i) Head mason 0.25 No. @ 350 each = 87.5
(ii) Mason 1 No. @ 250 each = 250
(iii) Ordinary labour 1 No. @ 150 each = 150
(d) Washing of sand, local carriage, scaffolding, curing, & sundries etc. L.S. = 150
Total = 899.3
Profit 0.1 = 89.93
Overhead 0.035 = 31.48
= 1020.71
Add VAT with adjustment factor 1.04712 0.045 = 48.1
Grand total = 1068.81
Average of A & B = 1224.38
(i) Ground floor Rate per sft = 12.24
Rate per sqm. = 131.75
Say, 132 .00 Per sqm.