Break Up Details (Don's use Rate, its PWD rate 2008)

Construction of 1'-0" clear width and depth upto 1'-0" masonry surface drain
(a) Earth work in excavation:
10'-0" x 1'-10" x 1'-3"(av.)= 22.92 cft. @ 1412.5 Per % 0 cft. = 32.37
(b) Brick-flat soling:
10'-0" x 1'-10"= 18.33 sft. @ 1830 Per % sft. = 335.44
(c) Cement concrete (1:3:6):
10'-0" x 1'-10" x 0'-3"(av.)= 4.58 cft. @ 11182.5 Per % cft. = 512.16
(d) 5" thick brick work (1:4):
2 x 10'-0" x 0'-9"= 15 sft. @ 4499.25 Per % sft. = 674.89
(e) 1/2" thick cement plast:er (1:4)
with neat cement finish:
10'-0" x 4'-0"= 40 sft. @ 1358 Per % sft = 543.2
Total = 2098.06
Profit 0.1 = 209.81
Overhead 0.035 = 73.43
= 2381.3
Add VAT with adjustment factor 1.04712 0.045 = 112.21
Grand total = 2493.51
Rate per rft.. = 249.35
Rate per rm = 818.12
Say, 818 .00 Per rm.