Break Up Details (Don's use Rate, its PWD rate 2008)

Supplying and laying, fitting, fixing of 9" or 225 mm inside dia RCC pipe excluding cost
of earth cutting & back filling.
Considering 18 rft. of work
(a) Cost of machine made best quality 9" dia RCC
pipe in/c all necessary fittings 18 rft. @ 125 each = 2250
(b) Sand filling 20 cft. @ 750 Per % sft. = 150
(c) Cement concrete(1:3:6) at 3 nos. joint 3.93 cft. @ 11182.5 Per % cft. = 439.47
(d) Labour charge for laying pipe maintaining proper
slope in/c cost of gasket etc.
(i) Head mason 0.25 No. @ 350 each = 87.5
(ii) Mason 0.25 No. @ 250 each = 62.5
(iii) Skilled labour 1 No. @ 200 each = 200
Total = 3189.47
Profit 0.1 = 318.95
Overhead 0.035 = 111.63
= 3620.05
Add VAT with adjustment factor 1.04712 0.045 = 170.58
Grand total = 3790.63
Rate per rft. = 210.59
Rate per rm. = 690.95
Say, 691 .00 Per rm.