Break Up Details (Don's use Rate, its PWD rate 2008)

Labour for compacted sub-base base course
Consider 10cum (353.15 cft.) of work
1. Bricks 2594 Nos. @ 5000 per %0 = 12970
2 Ordinary labour for breaking bricks 14 Nos. @ 150 each = 2100
3 Labour for spreading
(a) Mason 1 Nos. @ 250 each = 250
(b) Labour 12 Nos. @ 150 each = 1800
4 Labour for watering 1.75 No. @ 150 each = 262.5
5 Cost of sand (F.M = 0.8) 4.32 cft. @ 750 Per % cft. = 32.4
6 Hire charge of 8 ton to 12 ton road
roller (two steel drum roller) 0.06 day @ 4000 Per day = 240
7 Fuel & lubricants, spares,
maintenance, driver etc. 0.06 day @ 1000 Per day = 60
8 Local carries Sundries T & P etc. L. S. 50
Total = 17764.9
Profit 0.1 = 1776.49
Overhead 0.035 = 621.77
= 20163.16
Add VAT with adjustment factor 1.04712 0.045 = 950.1