Break Up Details (Don's use Rate, its PWD rate 2008)

Providing tack coat @ 15 Ibs per 100 sft.
Considering 100 sft. of work
(a) Cost of materials
(i) Bitumen 15 lbs. @ 18.14 Per Ib. = 272.1
(ii) Fire wood 0.25 Mds. @ 150 Per mnd. = 37.5
Total (a) = 309.6
(b) Labour charges:
(i) Skilled labour for heating
& laying bitumen 0.5 No. @ 200 each = 100
(ii) Sundries and T & P L.S. = 18.75
Total (c) 118.75