Break Up Details (Don's use Rate, its PWD rate 2008)

Providing bitumenous painting with 4.54 kg of bitumin per 10 sqm. Road surface.
Considering 100 sft. of work
(a) Cost of materials
(i) Bitumen 10 lbs. @ 18.14 Per Ib. = 181.4
(ii) Sand (F.M. 1.2) 3 cft. @ 1300 Per % cft. = 39
(iii) Fire wood 0.5 mnd. @ 150 Per mnd. = 75
Total (a) = 295.4
(b) Labour charges:
(i) Skilled labour for heating & laying mixture
of bitumen and pea-gravels 0.5 No. @ 200 each = 100
(ii) Labour for spreading sand 0.2 No. @ 150 each = 30
(iii) Head mason 0.0625 No. @ 350 each = 21.88
(iv) Mason 0.2 No. @ 250 each = 50
(v) Sundries and T & P L.S. = 30
Total (b) 231.88