Break Up Details (Don's use Rate, its PWD rate 2008)

Providing road marking in two course
Considering 100 sft. of work
1. Painter 1 No. @ 300 each = 300
2. Ordinary labour 1 No. @ 150 each = 150
3. Helper to painter 1 No. @ 200 each = 200
4. Synthetic anamel Paint 1.5 liter @ 207 Per liter = 310.5
5. Sealer 1 liter @ 129 Per liter = 129
6. Thinner 1 liter @ 85 Per liter = 85
7 T & P local carriege Sundries L.S. 100
1174.5
Profit 0.1 = 117.45
Overhead 0.035 = 41.11
= 1333.06
Add VAT with adjustment factor 1.04712 0.045 = 62.81
Grand total = 1395.87
Rate per sft. = 13.96
Rate per sqm. = 150.27
Say, 150 .00 Per sqm.