Break Up Details (Don's use Rate, its PWD rate 2008)

Labour for compacted water bound macadam base course
Consider 20'-0" x 10'-0" x 0'-6"= 100 cft. of work
1. Ordinary labour for spreading
in/c local carriage 1.5 Nos. @ 150 each = 225
2. Labour for hand packing 0.25 No. @ 150 each = 37.5
3. Labour for watering 0.5 No. @ 150 each = 75
4. Cost of sand for blinding 8 cft. @ 750 Per % cft. = 60
5. Labour for blinding 0.25 No. @ 150 each = 37.5
6. Head mason 0.0625 No. @ 350 each = 21.88
7. Mason 0.25 No. @ 250 each = 62.5
8. Hire charge of 8 ton to 12 ton road
roller (two steel drum roller) 0.1 day @ 4000 Per day = 400
9. Fuel & lubricants, spares,
maintenance, driver etc. 0.1 day @ 1000 Per day = 100