Break Up Details (Don's use Rate, its PWD rate 2008)

Carrying and placing/stacking of all sorts of rubbish/debris, bricks, brick-bats, gravels, chips etc.
Considering 100 cft. of work
(a) Ordinary labour for carrying by head-load to a safe distance
not exceeding 200'-0" 1 Nos. @ 150 each = 150
(b) Tools and plant, sundries etc. L.S. = 10
Total = 160
Profit 0.1 = 16
Overhead 0.035 = 5.6
= 181.6
Add VAT with adjustment factor 1.04712 0.045 = 8.56
Grand total = 190.16
Rate per cft. = 1.9
Rate per cum. = 67.1
Say, 67 .00 Per cum.