Item 01.2.6
Logistic support to monthly progress meeting between Contractor and Emplyer at the Engineer's office at site
1. Logistic support to arrange and conducting progress meeting L.S. = 1500
2. Incidental, sundries etc. L.S. = 200
Total = 1700
Profit 0.1 = 170
Overhead 0.035 = 59.5
1929.5
Add VAT with adjustment factor 1.04712 0.045 = 90.92
Grand total = 2020.42
Say, 2020 .00 each month