Item 01.4
Mobilization, cleaning site before commencing actual Physical works and demobilization
on completion of work
Considering a site of 5000 sft. Ground area
1. Contractor's site office, store, stackyard, Labour shed, service
connections, toilet facilities etc. cleaning site L.S. = 40000
2. Cleaning and removal L.S. = 10000
Total = 50000
Profit 0.1 = 5000
Overhead 0.035 = 1750
56750
Add VAT with adjustment factor 1.04712 0.045 = 2674.08
Grand total = 59424.08
Rate per sft. = 11.88
Rate per sqm. = 127.88
Say, 128 .00 Per sqm.