Item 02.10.1
Sand filling in foundation and plinth with local sand (F.M. 0.5 to 0.80)
Considering 100 cft. of work
1. Sand (F.M. 0.5 to 0.8) considering additional
30% for compaction 130 cft. @ 750 Per % cft. = 975
2. Head mason 0.125 No. @ 350 each = 43.75
3. Labour for levelling,
compacting, watering etc. 0.666666666666667 No. @ 150 each = 100
4. Sundries, T & P etc. L.S. = 15
Total = 1133.75
Profit 0.1 = 113.38
Overhead 0.035 = 39.68
1286.81
Add VAT with adjustment factor 1.04712 0.045 = 60.64
Grand total = 1347.45
Rate per cft. = 13.47
Rate per cum. = 475.69
Say, 476 .00 Per cum.