Item 02.10.3
Sand filling in foundation and plinth with local sand (F.M. 2.2)
Considering 100 cft. of work
1. Sand (F.M. 2.2) considering additional
30% for compaction 130 cft. @ 2200 Per % cft. = 2860
2. Head Mason 0.125 No. @ 350 each = 43.75
3. Labour for levelling, compacting etc.
watering etc. 0.666666666666667 No. @ 150 each = 100
4. Sundries, T & P etc. L.S. = 15
Total = 3018.75
Profit 0.1 = 301.88
Overhead 0.035 = 105.66
3426.29
Add VAT with adjustment factor 1.04712 0.045 = 161.45
Grand total = 3587.74
Rate per cft. = 35.88
Rate per cum. = 1267.1
Say, 1267 .00 Per cum.
Card image cap
Card title

This is a wider card with supporting text below as a natural lead-in to additional content. This content is a little bit longer.

Last updated 3 mins ago