Item 02.13
Earth filling in foundation trenches and plinth (earth available at site)
Considering 1000 cft. of work
1. Labour for filling
including local carriage 8 Nos. @ 150 each = 1200
3. Skilled labour for dressing
& consolidation 2 Nos. @ 200 each = 400
4. Sundries, T & P etc. L.S. = 75
Total = 1675
Profit 0.1 = 167.5
Overhead 0.035 = 58.63
1901.13
Add VAT with adjustment factor 1.04712 0.045 = 89.58
Grand total = 1990.71
Rate per cft. = 1.99
Rate per cum. = 70.28
Say, 70 .00 Per cum.