Item 02.14
Carriage of excavated earth from the construction site by truck or any other means
to the selected government land within metropolitan area
Break-up for 1000 cft = 1150 cft loose earth
1. Ordinary labour for cutting,
loading and unloading 7 No. @ 150 each = 1050
2. Skilled labour 1.5 No. @ 200 each = 300
3. Truck fare 6 trips @ 800 trip = 4800
4. Ordinary labour for local carriage,
leveling and dressing etc. 3 No. @ 150 each = 450
5. Tools and plant, sundries etc. LS = 37.5
Total = 6637.5
Profit 0.1 = 663.75
Overhead 0.035 = 232.31
= 7533.56
Add VAT with adjustment factor 1.04712 0.045 = 354.98
Grand total = 7888.54
Rate per cft. = 7.89
Rate per cum. = 278.64
Say 279 .00 per cum.