Item 02.15.1
Earth filling in foundation trenches with carted earth carried by truck or any other means
Considering 1000 cft. of work in/c compacting, dressing and local carriage
For Dhaka Metropolitan Area
Loose earth required in/c 15% shrinkage = 1150 cft.
1. Royalty for earth 1150 cft. @ 300 Per % 0 cft. = 345
2 Truck hire charge including cost of labour for loading and unloading 6 Trucks @ 800 Per truck = 4800
3 Labour for local carriage, levelling & compacting etc. complete:
(a) Ordinary labour 6 Nos. @ 150 each = 900
(b) Skilled labour 1 No. @ 200 each = 200
4 Sundries, T & P etc. L.S. = 45
Total = 6290
Profit 0.1 = 629
Overhead 0.035 = 220.15
7139.15
Add VAT with adjustment factor 1.04712 0.045 = 336.4
Grand total = 7475.55
Rate per cft. = 7.48
Rate per cum. = 264.16
Say, 264 .00 Per cum.