Item 02.15.2
Earth filling in foundation trenches with carted earth carried by truck or any other means
Considering 1000 cft. of work in/c compacting, dressing and local carriage
For Chittagong / Sylhet/ Narayanganj Area
Loose earth required in/c 15% shrinkage = 1150 cft.
1. Royalty for earth 1150 cft. @ 300 Per % 0 cft. = 345
2 Truck hire charge including cost of labour for loading and unloading 6 Trips @ 700 Per trip = 4200
3 Labour for local carriage, levelling & compacting etc. complete:
(a) Ordinary labour 6 Nos. @ 150 each = 900
(b) Skilled labour 1 No. @ 200 each = 200
4 Sundries, T & P etc. L.S. = 45
Total = 5690
Profit 0.1 = 569
Overhead 0.035 = 199.15
6458.15
Add VAT with adjustment factor 1.04712 0.045 = 304.31
Grand total = 6762.46
Rate per cft. = 6.76
Rate per cum. = 238.73
Say, 239 .00 Per cum.