Item 02.15.3
Earth filling in foundation trenches with carted earth carried by truck or any other means
Considering 1000 cft. of work in/c conmpacting, dressing and local carriage
For Rajshahi / Barishal / Khulna metropolitan area
Loose earth required in/c 15% shrinkage = 1150 cft.
1. Royalty for earth 1150 cft. @ 300 Per % 0 cft. = 345
3. Truck hire charge including cost of labour for loading and unloading 6 Trips @ 650 Per trips = 3900
4. Labour for local carriage, levelling & compacting etc. complete:
(a) Ordinary labour 6 Nos. @ 150 each = 900
(b) Skilled labour 1 No. @ 200 each = 200
5. Sundries, T & P etc. L.S. = 45
Total = 5390
Profit 0.1 = 539
Overhead 0.035 = 188.65
6117.65
Add VAT with adjustment factor 1.04712 0.045 = 288.27
Grand total = 6405.92
Rate per cft. = 6.41
Rate per cum. = 226.37
Say, 226 .00 Per cum.