Item 04.11
Extra rate (for per meter increase of height) over the rate of '4.2 to 4.9 where free
height of the structure exceeds 4 meter.
Considering 100 cft. of work
1. Extra head mason 0.05 No. @ 350 each = 17.5
2. Extra mason 0.2 No. @ 250 each = 50
3. Extra skilled labour 0.1 No. @ 200 each = 20
4. Extra ordinary labour 0.3 No. @ 150 each = 45
5. Extra for scaffolding 12.5 sft. @ 5 Per sft. = 62.5
6. Extra for local carriage, storage & sundries etc. ( 10% of ordinary labour rate) L.S. = 15
Total = 210
Profit 0.1 = 21
Overhead 0.035 = 7.35
238.35
Add VAT with adjustment factor 1.04712 0.045 = 11.23
Grand total = 249.58
Rate per cft. = 2.5
Rate per cum. = 88.29
Say, 88 .00 Per cum.