Item 04.25
3" thick cement concrete (C.C.) in floor (1:3:6)
Considering 100 sft. of work
From item No.-03.4.2 cost of concrete = 11182.5
1. For 3" thick 100 sft of work = 2795.63
2. Add extra for floor casting: Mason 1 No. @ 250 each = 250
Total = 3045.63
Profit 0.1 = 304.56
Overhead 0.035 = 106.6
3456.79
Add VAT with adjustment factor 1.04712 0.045 = 162.89
Grand total = 3619.68
Rate Per sft = 36.2
Rate Per sqm. = 389.66
Say, 390 .00 Per sqm.