Item 05.9.1
10 mm thick (finished) coloured mosaic on wall with Indian chips
Considering 100 sft. of work
A. Cost of materials, labour in/c T & P:
Same as item No. 5.5.1 100 sft. @ 7524.67 Per % sft. = 7524.67
B. Add for colour pigment 8 Ibs @ 45 Per Ib. = 360
Total = 7884.67
Profit 0.1 = 788.47
Overhead 0.035 = 275.96
8949.1
Add VAT with adjustment factor 1.04712 0.045 = 421.69
Grand total = 9370.79
(i) Ground floor Rate per sft. = 93.71
Rate per sqm = 1008.69
Say, 1009 .00 Per sqm.