Item 05.9.2
10mm thick (finished) coloured mosaic on wall with Pakistani chips
Considering 100 sft. of work
A. Cost of materials, labour in/c T & P:
Same as item No. 5.5.2 100 sft. @ 8149.67 Per % sft. = 8149.67
B. Add for colour pigment 8 Ibs @ 45 Per Ib. = 360
Total = 8509.67
Profit 0.1 = 850.97
Overhead 0.035 = 297.84
9658.48
Add VAT with adjustment factor 1.04712 0.045 = 455.11
Grand total = 10113.59
(i) Ground floor Rate per sft. = 101.14
Rate per sqm = 1088.67
Say, 1089 .00 Per sqm.