Item 08.7
Supplying, fitting and fixing 10" wide 16 SWG Aluminium Sheet water stopper in construction joint of RCC vertical
wall etc.
Break-up for 20 rft. work
1. 16 BWG Aluminium sheet
1 x 20'-0" x 10" = 16.6 sft.
Wastage 5% = 0.83 sft.
17.43 sft.
= 3.77 kg @ 300 Per kg. = 1131
3. Labour for fitting, fixing in position
(i) Mason 0.2 Nos. @ 250 each = 50
(ii) Skilled Labour 0.2 Nos. @ 200 each = 40
4. G.I. Wire, nails etc. L.S. = 29.17
5. Tools and plants, sundries etc. L.S. = 12.5
Total = 1262.67
Profit 0.1 = 126.27
Overhead 0.035 = 44.19
= 1433.13
Add VAT with adjustment factor 1.04712 0.045 = 67.53
Grand total = 1500.66
Rate per rft. = 75.03
Rate per rm = 246.17
Say 246 .00 per rm.