Item 10.3.1
Galvanized iron plain sheet ridging with galvanized bolts and nuts
Considering 9.1 (30 rft) meter. of work
(i) Price considering 10% laping 10.01 rm @ 218.73 Per rm = 2189.49
(ii) Screws, limpet, washer etc. 0.15 = 328.42
(iii) Carpenter 1 No. @ 300 each = 300
(iv) Helper to carpenter 1 No. @ 200 each = 200
Total= 3017.91
Profit 0.1 = 301.79
Overhead 0.035 = 105.63
= 3425.33
Add VAT with adjustment factor 1.04712 0.045 = 161.4
Grand total = 3586.73
Rate per rm = 392.27
Say, 392 .00 per rm