Item 10.3.2
Colored iron plain sheet ridging with galvanized bolts and nuts
Considering 9.1 meter. (30 rft) of work
(i) Price considering
10% laping 10.01 rm @ 246.08 Per rm = 2463.26
(ii) Screws, limpet washer etc. 0.15 = 369.49
(iii) Carpenter 1 No. @ 300 each = 300
(iv) Helper to carpenter 1 No. @ 200 each = 200
Total= 3332.75
Profit 0.1 = 333.28
Overhead 0.035 = 116.65
= 3782.68
Add VAT with adjustment factor 1.04712 0.045 = 178.24
Grand total = 3960.92
Rate per rm = 433.19
Say, 433 .00 per rm