Item 11.7.3
Supply and making hand-rails of stair case including necessary moulding
Considering, 1 x 9'-6" x 2.75" x 6.25"= 1.134 cft. of work
For Mehgoni wood
(a) Cost of wood 1.1907 cft. @ 1350 Per cft. = 1607.45
(b) Labour for making rails
(i) Carpenter 0.75 No. @ 300 each = 225
(ii) Carpenter helper 0.5 No. @ 200 each = 100
(c) Fitting, fixing in position in/c corner finishing
(i) Carpenter 0.5 No. @ 300 each = 150
(ii) Carpenter helper 0.5 No. @ 200 each = 100
Total = 2182.45
Profit 0.1 = 218.25
Overhead 0.035 = 76.39
= 2477.09
Add VAT with adjustment factor 1.04712 0.045 = 116.72
Grand total = 2593.81
Rate per cft = 2287.31
Rate per cum. = 80776.35
Say 80776 .00 Per cum.