Item 24.20
Providing bitumenous painting with 4.54 kg of bitumin per 10 sqm. Road surface.
Considering 100 sft. of work
(a) Cost of materials
(i) Bitumen 10 lbs. @ 18.14 Per Ib. = 181.4
(ii) Sand (F.M. 1.2) 3 cft. @ 1300 Per % cft. = 39
(iii) Fire wood 0.5 mnd. @ 150 Per mnd. = 75
Total (a) = 295.4
(b) Labour charges:
(i) Skilled labour for heating & laying mixture
of bitumen and pea-gravels 0.5 No. @ 200 each = 100
(ii) Labour for spreading sand 0.2 No. @ 150 each = 30
(iii) Head mason 0.0625 No. @ 350 each = 21.88
(iv) Mason 0.2 No. @ 250 each = 50
(v) Sundries and T & P L.S. = 30
Total (b) 231.88